Prince2 Interview Questions and Answers for freshers & experienced:
Prince2 stand for PRojects IN Controlled Environments(PR-IN-C-E2). It is one of the most leading project management methodology. It is used by people and organizations in arrange of different industries. PRINCE2 was developed as a UK government standard for information systems projects.Prince2 is widely recognized and used in the different private sector, both in the UK and internationally. The Prince2 method is in the public domain, and offers non-proprietorial best practise guidance on project management.
PRINCE2® 7th Edition was released in September 2023. Here are some of the key changes in the new edition:
A focus on agile and hybrid approaches: PRINCE2® 7th Edition acknowledges the increasing popularity of agile and hybrid project approaches. The framework has been updated to make it more adaptable to these approaches, while still maintaining its core principles.
A stronger focus on value: The new edition places a greater emphasis on the concept of value. Project managers are now required to define the value that the project is expected to deliver, and to track and measure this value throughout the project lifecycle.
A more risk-aware approach: The new edition of PRINCE2® takes a more risk-aware approach to project management. Project managers are now required to identify and assess risks early in the project lifecycle, and to develop plans to mitigate these risks.
A more collaborative approach: The new edition of PRINCE2® emphasizes the importance of collaboration between project stakeholders. Project managers are now required to build relationships with stakeholders and to involve them in decision-making throughout the project lifecycle.
Overall, PRINCE2® 7th Edition is a more modern and adaptable framework that reflects the changing needs of the project management landscape.
Here are some additional details about the changes in PRINCE2® 7th Edition:
The seven principles have been updated: The seven principles of PRINCE2® have been updated to reflect the changing nature of project management. The new principles are:
Continued business justification
Tailoring
Clearly defined roles and responsibilities
Manage by stages
Defined product delivery
Managing by exception
Configuration management
The seven themes have been reorganized: The seven themes of PRINCE2® have been reorganized to make them more consistent with the new principles. The new themes are:
Business case
Organization
Plans
Quality
Risk
Change
Progress
The processes have been updated: The seven processes of PRINCE2® have been updated to reflect the new principles and themes. The new processes are: Starting up a project and Initiating a project Planning Controlling a project Managing stage boundaries Closing a project
The guidance has been updated: The guidance for using PRINCE2® has been updated to reflect the new principles, themes, and processes. The new guidance includes more examples and case studies to help project managers apply the framework in practice.
Define Prince2?
Prince2 stands for Project IN Controlled Environment. It is a process-based method which is used for effective project management.
What is Prince2, and how does it differ from other project management methodologies?
Prince2 is a widely used project management methodology that provides a structured approach for managing projects. Unlike some other methodologies, Prince2 is process-based and provides a clear framework for project initiation, planning, execution, monitoring, and closure. It emphasizes the importance of defining clear project objectives, roles, and responsibilities, and ensures that projects are constantly monitored and controlled to ensure successful outcomes.
What are the key principles of Prince2?
Prince2 is based on seven key principles:
Continued Business Justification: The project should make sense economically and strategically throughout its lifecycle.
Learn from Experience: Past experiences, both positive and negative, should be used to improve project performance.
Defined Roles and Responsibilities: Clear roles and responsibilities should be assigned to each project team member to ensure accountability and effective decision-making.
Manage by Stages: Projects should be divided into manageable stages, each with predefined objectives and deliverables.
Manage by Exception: Authority levels should be established and utilized to enable efficient decision-making at various levels of the project.
Focus on Products: The project should be product-focused, with well-defined deliverables at each stage. Tailor to Suit the Project Environment: Prince2 should be tailored to fit the specific needs of each project, taking into account its size, complexity, and context.
What are the main components of a Prince2 project?
Prince2 projects consist of the following components:
Project Board: The Project Board is responsible for providing overall direction and management of the project. It comprises the Executive, Senior User, and Senior Supplier roles.
Project Manager: The Project Manager is responsible for day-to-day management of the project, ensuring that it stays on track and delivers the expected outcomes.
Team Manager: Team Managers are responsible for managing specific teams and delivering the products within their assigned areas.
Project Assurance: This role ensures that the project is being conducted following Prince2 principles and provides independent assessment and advice to the Project Board.
Change Authority: The Change Authority is responsible for assessing and approving changes to the project’s baseline.
Project Support: Project Support provides administrative and logistical support to the Project Manager and the rest of the project team.
What are the different Prince2 management stages, and why are they important?
Prince2 defines the following management stages:
Starting Up a Project (SU): This is the pre-project phase where the project’s feasibility is assessed, and the Project Brief and initiation documentation are created. It determines whether the project should proceed to the next phase.
Initiating a Project (IP): In this phase, the detailed project plan is created, including the Business Case, Project Initiation Documentation (PID), and the project approach. The project team is appointed, and roles and responsibilities are defined.
Controlling a Stage (CS): This phase involves the day-to-day management of the project. Progress is monitored, and issues and risks are addressed. At the end of this stage, a decision is made whether to continue to the next stage.
Managing Product Delivery (MP): This stage focuses on the creation and delivery of project products. Team Managers are responsible for their respective areas.
Managing a Stage Boundary (SB): This phase comes at the end of each management stage and involves reviewing progress, updating the plan, and reporting to the Project Board. The decision to proceed with the next stage is taken in this phase.
Closing a Project (CP): In this final phase, the project is formally closed. The final product is handed over to the customer, and a Post-Project Review is conducted to capture lessons learned.
Can you explain the difference between the Project Board and the Project Manager in Prince2?
The Project Board and Project Manager are distinct roles in Prince2 with different responsibilities:
Project Board: The Project Board is responsible for providing strategic direction and decision-making for the project. It oversees the project’s progress, approves major decisions, and ensures that the project aligns with the organization’s objectives. The Project Board consists of the Executive, Senior User, and Senior Supplier roles.
Project Manager: The Project Manager is responsible for the day-to-day management of the project. They develop and maintain the project plan, manage risks and issues, report progress to the Project Board, and ensure that the project stays on track to deliver the expected outcomes.
How does Prince2 handle project risks, and what are the key risk management activities?
Prince2 employs a proactive approach to risk management. The key risk management activities include:
Identify Risks: The project team identifies potential risks that could impact the project’s objectives. Risks are recorded in the Risk Register.
Assess Risks: The identified risks are assessed in terms of their potential impact and probability of occurrence. This helps prioritize which risks need attention.
Plan Responses: Risk responses are developed for the identified risks. These responses could include risk mitigation, contingency plans, or transferring the risk to a third party.
Implement Responses: The risk responses are put into action to address the identified risks.
Monitor Risks: Throughout the project, risks are regularly reviewed and monitored. New risks may emerge, and the status of existing risks may change. The Risk Register is updated accordingly.
What is the purpose of the Business Case in Prince2, and why is it important?
The Business Case in Prince2 justifies the project from a business perspective. It provides a thorough assessment of the project’s expected benefits, costs, risks, and the reason for undertaking the project. The Business Case is created during the Initiating a Project process and is continually reviewed and updated throughout the project.
The importance of the Business Case lies in the fact that it serves as a foundation for decision-making throughout the project’s lifecycle. It helps stakeholders understand why the project is being undertaken and whether it is still viable and aligned with the organization’s objectives. The Business Case is used by the Project Board to assess the project’s continued viability and to make critical decisions, such as whether to proceed to the next project stage or even to terminate the project if the business justification is no longer valid.
What are the key features of prince 2?
The key features are –
Widely organized and understood
Can be applied to any project
Based on management by exception
Invaluable diagnostic tool
Consistency and reusability in project work.
What are the levels of plan?
The levels of plan are –
Project Plan
Stage Plan
Team Plan
Exception Plan
What are the planning steps?
The Planning steps are –
Designing the pal
Define the products
Identify Activities and Dependencies
Prepare Estimates
Prepare Schedule
Document plan
Identify Risks
What is directing a project (DP)?
It performs-
Support project
Accept Results
Provides Management Approval
Which role is responsible for producing a Product Status Account?
Project Support responsible for producing a Product Status Account.
Which role is responsible for drafting the outline Business Case?
Executive is responsible for drafting the outline Business Case.
Which role confirms stage and project progress against agreed tolerances?
Project Assurance confirms stage and project progress against agreed tolerances.
What are the two types of progress controls provided by PRINCE2?
The two types of progress controls provided by PRINCE2 are –
Time-driven
Event-driven
Which process triggers the request to deliver a project?
Initiating a Project process triggers the request to deliver a project.
Who is responsible for communicating with stakeholders?
Project Board is responsible for communicating with stakeholders.
Which process can be carried out without using PRINCE2?
Managing Product Delivery process can be carried out without using PRINCE2.
Which role maintains the Quality Register?
Project support maintains the Quality Register.
Which role has the responsibility of setting project tolerances?
Corporate or Program management has the responsibility of setting project tolerances.
Which document defines the acceptance criteria and roles for the project?
Project Product Description document defines the acceptance criteria and roles for the project. This is created in the Starting up a Project process and used during the Closing a Project process to help verify that the project has delivered to expectations.
What is the objective of the Directing a Project process?
The objectives are
To ensure there is authority to initiate, deliver and close the project
To ensure management direction and control are provided throughout the project and that the project remains viable
Plans for realizing post project benefits are managed and reviewed
What is the purpose of the Managing Product Delivery process?
The purpose of the Managing Product Delivery process is to control the link between the Project Manager and the Team manager(s).
What is the primary objective of the Quality Review Technique?
The primary objective of the Quality Review Technique is to involve key interested parties in promoting wider acceptance of the product.
What is the purpose of a Checkpoint Report?
The purpose of a Checkpoint Report is to updates the project Manager on the status of a Work Package.
What are the principles of Prince2?
The principles are –
Manage by stages
Focus on products
Manage by exception
Tailor to suit the project environment
Continued business justification
Learn from experience
Defined roles and responsibilities
What are the seven themes in Prince2
Business case
Organization
Quality
Plans
Risk
Change
Progress
What is the use of Prince2 method?
The PRINCE2 method is used to address project management through the four integrated elements of principles processes, the project environment and themes.
What is risk register?
It is a table which is used to contain the risks that may threaten the goal of the project.
What is the use of quality register?
Quality register is used to contain the details of all planned quality activities, personnel involved and dates.
What is issues register?
It is a set of notes about change requests, complaints, concerns and problems sent by all project members